The project team:
Tom Allen, Elizabeth Lovett, Frank Meloni, John Abitabilo
Construction Update | October 9, 2026
The big news this week is the arrival of our new transformer, supplied by PECO. To date our church has been served by a one-phase, basically residential electricity system (ingeniously jury-rigged year after year by our excellent Property Chairs). Our new three-phase system, in which the transformer (which will soon be underground) is a key piece, is necessary to support the geothermal project.
We’ve also received delivery of our new gas-fired water heater. This means we can get rid of the big oil tank which sits at the Parish Hall end of the building, and get out of the business of storing oil.
Progress is made every day on the guts of the project: placing pipe and conduits, hanging heat pumps and ERVs (units that will supply fresh air), etc. Pictured is ceiling demolition in the choir room, opening access to the last attic that will contain equipment. At this point the equipment has mostly been hung in the Day School, library, and kitchen attics.

Construction Update | October 2, 2026
The “pump room” (formerly the Day School boiler room) is taking shape. The pipes in the picture show where the water (mixed with ethylene glycol, basically antifreeze) will enter from (and be returned to) the three sections of the well field under the parking lot. The other picture shows equipment—pumps, expansion tanks, etc.—that will go in the pump room, to send ground-conditioned water to the heat pumps at various locations in our buildings.

Similarly, the new electricity room (formerly the main boiler room) is a beehive of activity. The second picture shows heavy-duty wire that will go from the pole on Righters Mill Road, through a transformer, to the new electricity room.

There’s progress everywhere, for example in the piping network that will carry water from the pump room to the heat pumps, and in the system of conduits to carry electricity. The organization required in this project is amazing. This is all coordinated by Matt Karp, our Superintendent from GreenerU. He’s doing a good job.
Construction Update | September 25, 2026
The hole in the Day School Frog Room ceiling (for hoisting equipment to the attic) is being closed. Soon there will be a new ceiling, with new and better lighting.
Progress is being made on the piping from the “pump room” (the old Day School boiler room) to the Day School attic (for the heat pump there) and from the Day School attic to the Library attic (for the heat pump there). This is two pipes, one for supply of ground-conditioned water and the other for return.
Most of the needed equipment has been hoisted into the Library and kitchen attics. See picture. When equipment is installed in an attic it is hung, rather than resting on the attic floor. That is essential to reduce vibration.
Areas where there were puddles in the parking lot, after our recent rain, have been addressed.
Downstairs, in our new Electricity Room (under the Parish Hall), the conduits (to bring electricity from our pole on Righters Mill) have been brought indoors, and the room has been readied to receive electrical equipment.
Those are just examples. There is activity all over the place.

Construction Update | September 18, 2026
Final blacktop is now on parking lot. Parking in the lot will be OK Sunday. Just imagine what is beneath this parking lot, never to be seen again!
Work going forward on piping: connecting the Day School boiler room (where the ground-conditioned water enters and exits) to the Day School attic, and from there to library and kitchen attics. Soon, a second circulation system of pipes will serve the other end of the buildings.
Some new electrical equipment installed. Also, important infrastructure installed in (old boiler)/new electrical room under Parish Hall.
Important progress with the conduits on the Righters Mill side, preparations in the basement….progress sort of everywhere.

Construction Update | September 11, 2026
The parking lot is usable as of Saturday, September 12th. Another coat of blacktop will go down in a few weeks, but is usable for driving and parking.
The originally specified natural gas generator was not available, but have now reached agreement on 100-KW diesel generator, capable of maintaining life safety and other critical systems during power outages.
Work is ongoing in several attics: vent work above the Day School, structural work above Library.
Lots of equipment (heat pumps, air handlers, pipes, vents, pumps, etc.) has been delivered and await installation. Much ancient equipment has been removed.
The Day School will operate out of Parish Hall until Day School construction is finished. The set-up in Parish Hall is GREAT. The Day School will be isolated from construction. Day School Orientation was yesterday…everybody was happy.

Construction Update | September 4, 2026
What stands out is how much is being done, in lots of different areas.
- In the basement, various old heating units have been removed, some of the necessary new piping has been placed, and all kinds of other preparations are being made.
- In the library and kitchen, openings have been made in the ceilings and some of the equipment has been hoisted into the attics.
- In the Day School attic, the heat pump and air exchange units are about to be hung in place.
- The parking lot has been graded, and the binding layer of asphalt will be put down soon…and we’ll have a parking lot again. We’ll let that settle awhile (parking and driving will be fine) to identify pooling areas if any, and then apply the final coat of asphalt.
- Taking advantage of the state of the parking lot, power has been run over to the playground…opening up opportunities for the Day School, Azalea D
ay, etc.
In other words, the construction is really cooking.

Construction Update | August 28, 2026