A PROJECT OF RENEWAL:
CONSTRUCTION STARTING SOON AT ST. C!
JUNE 3, 2026
Dear parishioners of St. Christopher’s Church,
Shortly after June 15, construction will start on our capital improvements. The biggest part of this project will be installation of a geothermal heating/cooling system in our buildings, including supply of fresh air and an overhaul of our electrical system.
This report will summarize what will be happening this summer, and what the schedule looks like. (Not much will be happening with the Sanctuary, so in all probability, services will continue there.) Then it will summarize how and why we got here, and how the financial side of this will work. You, parishioners of St. Christopher’s, have enthusiastically and generously supported our capital campaign and deserve to know as much as you have patience for! We also welcome any questions you may have.
Before getting in the weeds, we pause to thank Hillary Raining, whose vision we are carrying out, and our departed friend and mentor Perry Pepper, co-chair and major influence on this project, who would love to be in the mix right now.
WHAT WILL BE HAPPENING THIS SUMMER
This summer, starting around June 15, our design/builder GreenerU will supervise four major subs in installing a geothermal heating/cooling system in our buildings. Wells will be drilled in our parking lot area. Tubes will be installed in the wells to carry water down into the ground and back, having absorbed the constant temperature of the ground (around 51 degrees). Ground-conditioned water from the wells is to be piped into our building and then piped to heat pumps to be installed mostly in attic spaces around our campus. Next to the heat pumps, air exchange units will be installed to efficiently supply fresh air. Construction in our buildings will entail some intrusions into walls, breaking through ceilings, and restoration afterward.
At the same time, our electrical system will be upgraded from the present single-phase (basically residential) system we have been jury-rigging since 1950, to the three-phase commercial system we need. This will entail a new pole and transformer on the Righters Mill side of the church, new connections, and some new electrical equipment inside. We will be preserving equipment that is still useful, such as most of the wiring.
We will be installing a new standby generator to give our church more resilience in future emergencies. We also intend to refurbish the Parish Hall, get a new shed (the present one is falling down), and possibly do a couple other projects.
SCHEDULE
Construction will start with removal of the asphalt of most of the parking lot shortly after June 15. All summer, parking will still be available in the circle in front of the church, in the driveway to the Rectory, and on the grass as needed. Not much work involves the Sanctuary, and we anticipate it will be available all summer. But other building areas will be closed off as required:
Day School June 19
Offices July 3
Kitchen/Parish Hall July 17
Library July 24
…and re-opened upon completion, starting with the Day School in late August, offices (Sep 7-11), kitchen/Parish Hall (Sep 14-18), and Library (Sep 14-25). We are hoping to turn the system on in late October. We all have to understand that while the above schedule has been constructed to be realistic, stuff happens and there may be changes.