The project team:
Tom Allen, Elizabeth Lovett, Frank Meloni, John Abitabilo

Construction Update | October 9, 2026

The big news this week is the arrival of our new transformer, supplied by PECO. To date our church has been served by a one-phase, basically residential electricity system (ingeniously jury-rigged year after year by our excellent Property Chairs). Our new three-phase system, in which the transformer (which will soon be underground) is a key piece, is necessary to support the geothermal project.

We’ve also received delivery of our new gas-fired water heater. This means we can get rid of the big oil tank which sits at the Parish Hall end of the building, and get out of the business of storing oil.

Progress is made every day on the guts of the project: placing pipe and conduits, hanging heat pumps and ERVs (units that will supply fresh air), etc. Pictured is ceiling demolition in the choir room, opening access to the last attic that will contain equipment. At this point the equipment has mostly been hung in the Day School, library, and kitchen attics.

Top: Day School Attic Left: New transformer Right: Choir room

Construction Update | October 2, 2026

The “pump room” (formerly the Day School boiler room) is taking shape. The pipes in the picture show where the water (mixed with ethylene glycol, basically antifreeze) will enter from (and be returned to) the three sections of the well field under the parking lot. The other picture shows equipment—pumps, expansion tanks, etc.—that will go in the pump room, to send ground-conditioned water to the heat pumps at various locations in our buildings.

Similarly, the new electricity room (formerly the main boiler room) is a beehive of activity. The second picture shows heavy-duty wire that will go from the pole on Righters Mill Road, through a transformer, to the new electricity room.

There’s progress everywhere, for example in the piping network that will carry water from the pump room to the heat pumps, and in the system of conduits to carry electricity. The organization required in this project is amazing. This is all coordinated by Matt Karp, our Superintendent from GreenerU. He’s doing a good job.

Construction Update | September 25, 2026

The hole in the Day School Frog Room ceiling (for hoisting equipment to the attic) is being closed. Soon there will be a new ceiling, with new and better lighting.

Progress is being made on the piping from the “pump room” (the old Day School boiler room) to the Day School attic (for the heat pump there) and from the Day School attic to the Library attic (for the heat pump there). This is two pipes, one for supply of ground-conditioned water and the other for return.

Most of the needed equipment has been hoisted into the Library and kitchen attics. See picture. When equipment is installed in an attic it is hung, rather than resting on the attic floor. That is essential to reduce vibration.

Areas where there were puddles in the parking lot, after our recent rain, have been addressed.

Downstairs, in our new Electricity Room (under the Parish Hall), the conduits (to bring electricity from our pole on Righters Mill) have been brought indoors, and the room has been readied to receive electrical equipment.

Those are just examples. There is activity all over the place.

Library heat pump (barely visible) in upper left and brining electricity inside

Construction Update | September 18, 2026

Final blacktop is now on parking lot. Parking in the lot will be OK Sunday. Just imagine what is beneath this parking lot, never to be seen again!

Work going forward on piping: connecting the Day School boiler room (where the ground-conditioned water enters and exits) to the Day School attic, and from there to library and kitchen attics. Soon, a second circulation system of pipes will serve the other end of the buildings.

Some new electrical equipment installed. Also, important infrastructure installed in (old boiler)/new electrical room under Parish Hall.

Important progress with the conduits on the Righters Mill side, preparations in the basement….progress sort of everywhere.

Construction Update | September 11, 2026

The parking lot is usable as of Saturday, September 12th. Another coat of blacktop will go down in a few weeks, but is usable for driving and parking.

The originally specified natural gas generator was not available, but have now reached agreement on 100-KW diesel generator, capable of maintaining life safety and other critical systems during power outages.

Work is ongoing in several attics: vent work above the Day School, structural work above Library.

Lots of equipment (heat pumps, air handlers, pipes, vents, pumps, etc.) has been delivered and await installation. Much ancient equipment has been removed.

The Day School will operate out of Parish Hall until Day School construction is finished. The set-up in Parish Hall is GREAT. The Day School will be isolated from construction. Day School Orientation was yesterday…everybody was happy.

Construction Update | September 4, 2026

What stands out is how much is being done, in lots of different areas.

  • In the basement, various old heating units have been removed, some of the necessary new piping has been placed, and all kinds of other preparations are being made.
  • In the library and kitchen, openings have been made in the ceilings and some of the equipment has been hoisted into the attics.
  • In the Day School attic, the heat pump and air exchange units are about to be hung in place.
  • The parking lot has been graded, and the binding layer of asphalt will be put down soon…and we’ll have a parking lot again. We’ll let that settle awhile (parking and driving will be fine) to identify pooling areas if any, and then apply the final coat of asphalt.
  • Taking advantage of the state of the parking lot, power has been run over to the playground…opening up opportunities for the Day School, Azalea D
    ay, etc.

In other words, the construction is really cooking.

Construction Update | August 28, 2026

The pipes, to carry water from the wells under the parking lot (and to return water to those wells) are now entering the building, in the boiler room under the Day School. There they will connect to a manifold, and over the coming weeks a circulation system will be built, piping ground-conditioned water to heat pumps and returning building-conditioned water to the wells.

The pipes for that purpose are starting to accumulate.

For the most part, the heat pumps will be in attic spaces. The most difficult of those to access is over the Day School. Pictured below is the structure which has been built in the Frog Room to get a heat pump and air-handling unit into the Day School attic.

We’re getting an education in parking-lot construction. There is fully a foot of height difference between the surrounding sod and the graded dirt in the parking lot. That means that between some small stones and a couple applications of asphalt (a/k/a blacktop), the construction will be a foot deep.

You should check out the jobsite camera which has been recording site activities during daylight hours. A photo is taken every 10 minutes. We encourage everyone to click back to explore our progress. See the camera here (click the image for timelapse videos).

It’s now especially important that you coordinate visits to church (apart from Sunday) with the office.

Construction Update | August 21, 2026

Parking lot: Do you remember what this area looked like just a few days ago? The backfilling of all the trenches, while fast, has been anything but routine. All the recent digging produced way more big rocks than appropriate to lie under a parking lot. Many rocks have been removed, and better fill brought in. Next week will bring the final step in grading, to be followed by a layer of small rock, to be followed by re-paving.

Access to power: The conduits have mostly been buried, to bring power and fiber optic cable from the new telephone pole on Righters Mill, underground, to the building. Next step with these conduits is to get them into the building.

Inside: Next week the mechanical contractor will start the placement of heat pumps and associated work. First up is the heat pump and air exchanger to be hoisted into the attic of the Day School, to provide conditioned, fresh air through the ceilings of the classrooms.

Remember that construction tours are available from our Sexton John Abitabilo. Please coordinate through the office. And, it’s now especially important that you coordinate visits to church (apart from Sunday) with the office.

Construction Update | August 14, 2026

A lot is happening. We’ve received delivery of almost all the heat pumps that will be used, and they’ve mostly been placed in the area each will service. The well-drilling is done, and the inside work is proceeding. But the big story this week is trenching. In the parking lot area, trenches have been dug to connect the (completed) wells, and a lot of the necessary piping has been installed in the trenches. (That is all going to disappear under asphalt soon, so now would be a good time to visit if you’re curious.) Out back, a long trench is being dug from our new telephone pole, which is out near Righters Mill Road, to the building….to carry power, phone, and Internet, and to connect the back-up generator. And a big hole is being dug so that our new transformer can go underground.

The Sanctuary continues to be available for Sunday services. Besides attending services, please remember to coordinate any visits to church, beforehand, with the church office.

CONSTRUCTION TOURS: Our Sexton, John Abitabilo, has volunteered to take any interested parishioners around the construction, so you can see what is going on. We welcome your interest! Please coordinate through the church office.

TIMELAPSE CAMERA: For those traveling, we have a jobsite camera recording site activities during daylight hours. A photo is taken every 10 minutes. We encourage everyone to click back and explore our progress. This is a great way to share our project with others. See the camera here (click the image for timelapse videos).

This is an exciting project for our church, and we’ll be very happy to discuss it with you.

Construction Update | August 7, 2026

Lots of activity:

  • By the time you read this, the last of the geothermal wells will likely have been drilled. This exciting (but messy) phase of the project is done.
  • Next week, the construction team will begin connecting the wells together into 3 groups of 7. This will be done through trenches that will be dug for the piping connecting the wells to each other and to our buildings. These pipes will enter our church underground, in a utility room underneath the day school.
  • All that work will disappear under blacktop very soon, as the parking lot will then be restored, by early September. If you want to see the wells and their connections, we encourage you to visit, as once complete, these will disappear completely.
  • Inside, the work is ongoing to install heat pumps, air exchange units, and the necessary piping. There are intrusions into walls and ceilings, with restoration work to follow…an active construction site.
  • On the Righters Mill side of the church, we now have the new telephone pole, a “vault” to contain our new transformer underground, and the conduit for wiring. Trenching will start soon, for the electrical connection into the church.
  • Behind those scenes, we’re having discussions about Diocese support, gathering the information we’ll need to claim the federal credits, and many other important topics.

The Sanctuary continues to be available for Sunday services. Besides attending services, please remember to coordinate any visits to church, beforehand, with the church office.


A PROJECT OF RENEWAL:

CONSTRUCTION STARTING SOON AT ST. C!
JUNE 3, 2026

 

Dear parishioners of St. Christopher’s Church,

Shortly after June 15, construction will start on our capital improvements. The biggest part of this project will be installation of a geothermal heating/cooling system in our buildings, including supply of fresh air and an overhaul of our electrical system.

This report will summarize what will be happening this summer, and what the schedule looks like. (Not much will be happening with the Sanctuary, so in all probability, services will continue there.) Then it will summarize how and why we got here, and how the financial side of this will work. You, parishioners of St. Christopher’s, have enthusiastically and generously supported our capital campaign and deserve to know as much as you have patience for! We also welcome any questions you may have.

Before getting in the weeds, we pause to thank Hillary Raining, whose vision we are carrying out, and our departed friend and mentor Perry Pepper, co-chair and major influence on this project, who would love to be in the mix right now.

WHAT WILL BE HAPPENING THIS SUMMER

This summer, starting around June 15, our design/builder GreenerU will supervise four major subs in installing a geothermal heating/cooling system in our buildings. Wells will be drilled in our parking lot area. Tubes will be installed in the wells to carry water down into the ground and back, having absorbed the constant temperature of the ground (around 51 degrees). Ground-conditioned water from the wells is to be piped into our building and then piped to heat pumps to be installed mostly in attic spaces around our campus. Next to the heat pumps, air exchange units will be installed to efficiently supply fresh air. Construction in our buildings will entail some intrusions into walls, breaking through ceilings, and restoration afterward.

At the same time, our electrical system will be upgraded from the present single-phase (basically residential) system we have been jury-rigging since 1950, to the three-phase commercial system we need. This will entail a new pole and transformer on the Righters Mill side of the church, new connections, and some new electrical equipment inside. We will be preserving equipment that is still useful, such as most of the wiring.

We will be installing a new standby generator to give our church more resilience in future emergencies. We also intend to refurbish the Parish Hall, get a new shed (the present one is falling down), and possibly do a couple other projects.

SCHEDULE

Construction will start with removal of the asphalt of most of the parking lot shortly after June 15. All summer, parking will still be available in the circle in front of the church, in the driveway to the Rectory, and on the grass as needed. Not much work involves the Sanctuary, and we anticipate it will be available all summer. But other building areas will be closed off as required:

Day School June 19

Offices July 3

Kitchen/Parish Hall July 17

Library July 24

…and re-opened upon completion, starting with the Day School in late August, offices (Sep 7-11), kitchen/Parish Hall (Sep 14-18), and Library (Sep 14-25). We are hoping to turn the system on in late October. We all have to understand that while the above schedule has been constructed to be realistic, stuff happens and there may be changes.

Drilling the test well March 2026

HOW WE GOT HERE

All this is primarily driven by the Vestry’s decision, last fall, to install a geothermal system. That decision was made after a great deal of study led by Perry Pepper (until his untimely death), Elizabeth Lovett, Frank Meloni, Bill Thomas, and Tom Allen. There were two key moments/decisions. The first was the decision whether we need an air-conditioning system (as opposed to the present A/C in the Sanctuary and 18 noisy, inefficient window units). We decided “yes,” primarily because in the long term (our frame of reference), hot weather is occupying more and more of the calendar, and our buildings should always be usable. Once we said “yes” to that, any notion of reviving our obsolete gas-burning system for heat, and adding a system of outside compressors for cool, was impractical: expensive to build and run, noisy, ugly…a short-term fix at best. If we are to have compressors, they should be modern heat pumps, capable of both cooling and heating. And it’s time to stop burning gas.

Heat pump systems are of basically two kinds. The first kind is air-sourced: heat pumps sit outside and do the big job of taking both summer (say 90 degrees) and winter (say 25 degrees) air and producing the 68 degrees (or whatever) wanted inside. That’s actually the usual modern solution, but it takes a lot of electricity every month, and would entail large, noisy compressor-type machines sitting on pads outside our buildings.  The second kind of heat-pump system is geothermal: heat pumps sit inside and do the comparatively easy job of taking ground-conditioned water (at around 51 degrees) and producing air at the desired inside temperature. A geothermal system is the better alternative in every way….electricity use, noise, aesthetics, impact on the environment, expected life of system….except one: initial expense. Because you have to drill wells, a geothermal system is more expensive to install.

For most of 2025, we operated on the assumption that a geothermal system was too expensive, and we anticipated installing an air-sourced system. We were aware of the extremely generous credits available under federal law for geothermal, but we (and many others) expected those to go away in the Big Beautiful Bill last summer. But then, that bill took away credits and incentives for solar and wind, but left the geothermal credits untouched. That changed the calculus for us and led to our second key moment/decision.  The geothermal credit (30% of total project cost) and the American-made-equipment credit (which we are qualifying for…an additional 10% of total project cost) take the net cost of geothermal to basically the same as the net cost of the (much-worse) air-sourced system. We have done our homework on the viability of the geothermal credits, including consulting with the national accounting firm which specializes in this area, and which will be filing our claim for the credits.

Last fall we presented a great deal of information on alternatives and costs to the Vestry, which resolved that we should proceed with the geothermal option.

We had previously had some information-exchange with a design/build firm called GreenerU, which has been involved in installing sustainable HVAC at many universities and non-profits, including geothermal at Swarthmore College. A project we have followed closely, because it has substantial similarities with our situation (albeit ahead of us by about a year), has been the geothermal project at Wellesley Village Church in Wellesley, MA in which GreenerU has been the design/build partner….with successful completion and satisfied (“enthusiastic” would be a better word) leaders at the church. After the Vestry’s decision last fall, we re-initiated contact with GreenerU and started through a process which has involved engineering, design, a test well, an extensive bidding process, and (as of May 22) a final contract for construction. GreenerU is our design/builder and will be supervising four major subs: mechanical, electrical, drilling, and general construction.

GreenerU’s superintendent on site is Matt Karp. You may be at church and run into Matt; you should introduce yourself.  He’s very capable and you’ll like him. He and our excellent Sexton John Abitabilo are working together a lot.

PAYING FOR IT

You’re going to be looking at some big numbers here. As you do, please bear in mind that—if we’re planning for the future rather than doing some fix-up for a few years, leaving us again where we are now—this is expensive territory and it is subject to greater inflation than what we’ve all experienced as consumers. And, the initial expenditure will be greatly reduced by credits, as discussed below.

The geothermal project (including electrical overhaul and fresh-air supply) will initially cost around $5.2 million. Most of that is encompassed in our design/build contract with GreenerU. We will pay that amount over the balance of 2026. In 2027 we will file for two credits—the 30% credit for geothermal projects and the 10% credit for using equipment sufficiently made in America—in the amount of about $2 million.

The credit for geothermal projects was part of the Energy Policy Act of 2005. Its benefits were extended to non-profits (so that the credits are cash, rather than a credit against taxes due) by the Inflation Reduction Act of 2022. To the surprise of many, these credits survived the Big Beautiful Bill and are still law. There is no realistic path for that law to be changed so as to affect our project.

In addition to the geothermal project, we are getting a robust backup generator for future resilience in emergencies, and we are planning to refurbish the Parish Hall (better lighting, some painting, etc.), get a new shed, and maybe a couple other things. Total costs will be around $5.6 million. There will be a time delay before receipt of the credits, but the net expenditure should be around $3.6 million.

In our Capital Campaign to date, we have raised just shy of $3.5 million (including interest earned, and after our $100,000 contribution to the St. James Welcome Table in 2025 from Capital Campaign funds). Those are funds paid. In addition, based on existing pledges, we have around $200,000 coming in 2026 and $200,000 coming in 2027. Recognizing the time delay before receipt of the credits, we have planned to borrow (or spend from the Endowment) $1 or $1.2 million as “bridge” financing. All the above get us to within $500,000 to $700,000 of where we need to be for the initial expenditures. Based on conversations with parishioners in the course of the campaign, we are confident that that amount can and will be raised—without, it’s important to say, diminishing anybody’s understanding of the need for regular pledges, every year, for operating expenses.

If all goes as expected, once we get the credits in 2027 we’ll be able to repay the “bridge” financing and have a good amount left over to beef up the Endowment. For that to happen, it is true that a lot has to go right; but we have confidence in the construction plan and in GreenerU, and the credits are the law.

Bishop Gutiérrez at test well site

STEPPING BACK

Hillary’s charge to Perry Pepper and Tom Allen, about two years ago, was to develop a capital program for three purposes: (1) physical improvements (and we all knew HVAC was at the top of the list); (2) Outreach; and (3) Endowment. For the Outreach component, we decided on a substantial contribution to one project where we could really make a difference. We selected the St. James Welcome Table because it is terrific and because the federal government’s cutbacks were almost crippling some of its operations. We donated $100,000 to the Welcome Table in 2025.

Because of the generosity and commitment of our congregation….more than 100 families or individuals have pledged $3.85 million, of which almost $3.5 million has been paid….we can see our way clear to beefing up the Endowment. The credits we receive in 2027 should more than pay back the bridge financing discussed above, and the excess, which should be $6-800,000, will go to the Endowment. That will require a bit more fundraising now, but we are confident that will be accomplished.

It’s revealing about our congregation that we have received such very generous support for an HVAC project that, for the most part, nobody will see once it is done. It’s not like we’re building a new building. But you have understood the necessity of this. Your Vestry has also understood that while short-term fixes would be cheaper in the short run, it would be unreasonable to decline the opportunity to have 40% of our HVAC project costs paid by the federal government (in a project that very much fulfills the intentions of the federal laws cited above), in order for us to build the right system for our church. Besides the electricity-cost savings and the environmental and aesthetic advantages, the well-field we build is a permanent (referred to as 100-year) asset. In 10 or 40 years, as greener energy sources become available to PECO and to us, we’ll be in position to reduce our carbon footprint even more and maybe eliminate it.

We’re also breaking ground, demonstrating the feasibility of geothermal for a medium-size enterprise. We’ve attracted the interest of PA Interfaith Power and Light, the Diocese, and other organizations.

It’s risky to name names in this context, but it should be said that our Sexton John Abitabilo has been working very effectively on this project, and he’ll have big responsibilities this summer. Our Parish Administrator Shawna Minnucci and our Day School Director Brooke Cordes (both of whom will be temporarily displaced) have been participating in the planning process closely, and contributing very substantial input.

Elizabeth Lovett, architect and our Property Chair, is our prime representative in dealing with the construction. Frank Meloni (former Property Chair) and Bill Thomas (retired architect and Vestry member) have fully participated in the planning. Our Wardens Nancy Purcell (former Rector’s Warden), Peg Schofield (Rector’s Warden), and March Pepper (Accounting Warden) have actively monitored and participated in this process. We are fortunate to have this talent and dedication in our congregation.

Please do not hesitate to discuss this with any of us, or ask any questions. Many thanks for your support.

Tom Allen, Capital Campaign Chair